On 25 September 2026 the US Court of Appeals for the DC Circuit upheld, by two votes to one, the Defense Department's designation of the AI developer Anthropic as a supply-chain security risk. How far do a vendor's own contractual limits survive the buyer's procurement judgement? They do not override it. The court treated those limits themselves as a reason to doubt reliability, and the duty to verify fell back on the organisations that had been relying on them.

01A procurement decision can strip an AI vendor's safeguards of effect

The appeals court settled one point: a buyer may treat the usage limits an AI vendor writes into its contracts as evidence of unreliability. Judge Katsas wrote for the majority and Judge Rao joined him. Judge Henderson dissented.

The designation itself held that continued integration of Claude into the department's information systems amounted to a national-security risk of the kind the statute covers. The ruling found ample support for that conclusion. The risk identified was neither capability nor accuracy. It was the set of restrictions the vendor had imposed on itself.

Any organisation built on a vendor's safeguards now has reason to re-read those safeguards. Limits a vendor wrote for itself can become, in a buyer's hands, the ground for cutting supply off. Here that happened in Defense Department procurement. Leave the operation of those limits with the vendor, and what remains on the day supply stops is not yours to decide.

0241 U.S.C. §4713 was drafted against hostile states

The limits were read as unreliability. So where did the power to convert that reading into exclusion come from? The statute is 41 U.S.C. §4713, which gives the head of an executive agency authority to exclude a supplier on supply-chain risk grounds. Exclusion is decided by the head of the buying organisation, not by a court.

Figure 1 From stated limits to designation
§4713ScopenegotiatedLimitsretainedweapons,surveillanceJudgedunreliableSupply-chainrisk…Excludedfrom…§4713Scope negotiatedLimits retainedweapons, surveillanceJudged unreliableSupply-chain risk labelExcluded from procurement
Not the breakdown of talks but the continued presence of the limits supplied the material. The contested step is the third.

Judge Henderson's dissent went to the statute's reach. Section 4713 was drafted for cases where a hostile state or a bad actor works its way into a supply chain, she argued, not for a contractor that candidly honours its own stated limits. The statutory language is broad. On the dissent's reading, that broad language reached a party nobody had in mind when it was written.

The dissent did not change the outcome. The point about reach remains. If the same authority carries the same breadth, then the set of suppliers that can be excluded is wider than the drafters assumed.

03In medicines manufacture the duty to assess suppliers sits with the buyer

Under §4713 the government is the party that removes a supplier. In medicines manufacture the roles are reversed: the regulated party assesses the suppliers it uses.

Point of comparisonFederal procurement (§4713)Medicines manufacture (Annex 11)
Who removes the supplierThe head of an executive agency, by a covered procurement actionThe regulated manufacturer, on its own responsibility
Basis for the decisionA finding of supply-chain riskAn audit whose necessity follows from a risk assessment
Record left behindThe procedural record of the procurement actionA formal agreement stating responsibilities

EU GMP Annex 11 requires a formal agreement setting out responsibilities whenever a third party is used. It states that a supplier's capability and reliability are central to selection, and that the need for an audit follows from a risk assessment. An organisation that builds generative AI into a computerised system used in medicines manufacture does not step outside that assessing role.

Annex 11 is guidance for computerised systems in medicines manufacture, and it does not govern the material review process itself. What the comparison shows is narrow: which side of the transaction carries the duty to assess.

04The vendor that states its limits up front loses ground in procurement

Grant that the buyer assesses. What happens once that assessment is conducted in the language of reliability? This negotiation answers the question. The department demanded access for all lawful purposes. The company asked for an assurance that its model would not be used for fully autonomous lethal weapons or for domestic mass surveillance. Neither side gave way.

Figure 2 What happened to the side that disclosed first
Limits disclosed firstCalled uncertain inoperationsContract talks haltedRepurposed as groundsLimits disclosed firstCalled uncertain in operationsContract talks haltedRepurposed as grounds
Disclosure bought no credit and split into three outcomes. The right-hand branch is what this ruling settled.

The majority placed that unresolved dispute alongside Claude's built-in restrictions and concluded that the combination could make the system unreliable for military operations. The party that disclosed its limits first was penalised for the disclosure.

That direction of travel cuts against the vendor's own interest. A provider that writes out its permitted uses and publishes them lets buyers read how far they extend. The more specific those limits, the more confidently a buyer can find the point at which the product stops. A provider that publishes nothing hands over no such material. So long as procurement uses reliability in this sense, the provider that states no limits is the one that gets through. The content of the negotiation here comes from press reporting, not from the litigation record.

05Another federal court has held a parallel designation unlawful

Disclosure counted against the vendor. Yet this is not the only ruling in this area. In August a federal district court in San Francisco held a parallel government designation unlawful. Read together with a two-to-one split on appeal, the lawfulness of related designations varies by court and by level. The case name and whether that August ruling is final were not verified here.

What a buyer can count is not the number of rulings. It is the set of things that can be moved on the day supply stops.

1

A list of dependencies

Write down, by name, which process depends on which supplier.

2

A tested alternative

Run the same process through a second route at least once, in advance.

3

The selection record

Keep the reasons for choosing that supplier as they stood at the time of choosing.

Of the three, the record is the one that cannot be produced later. Reasons written after supply stops are reasons written by someone who already knows it stopped; they do not reconstruct the earlier judgement. The same holds for the alternative. An untested alternative is an alternative first tested on the day everything is already down.

06Procurement, legislation and records each shift responsibility

One court has held a parallel designation unlawful while another upholds this one. Where responsibility sits is not yet settled. The movement runs along three lines.

Figure 3 The order to settle before supply stops
ListdependenciesDefine thestop…Test onealternativeRecord theselectionList dependenciesDefine the stopconditionTest one alternativeRecord the selection
If the second step cannot be written as a number or an event, nothing after it moves. The fourth cannot be made later.

The first is procurement. A design that leaves AI safeguards in the vendor's hands collapses at the buyer's decision. Here it was not a technical failure that caused the collapse but a single administrative judgement. Redesigning therefore starts with whose hands hold the safeguards, not with how strong they are.

The second is what legislation actually rewards. If disclosing limits costs a vendor in procurement, disclosure will thin out. Judge Henderson noted that §4713 was not written with candid contractors in mind. Leave a broad authority pointed at parties it was never aimed at, and the rational vendor response becomes silence.

The third is the route by which outsiders verify anything. The courts disagree. Meanwhile at least six senators have co-sponsored a bill to protect employees of AI companies who report legal violations or safety failures. Alongside the courts, that bill would set up reporting from inside as a second route.

1

A further appeal

The company has said only that it is weighing its options; it has not said it will appeal.

2

Spread to other buyers

Nothing indicates whether procurement outside the Defense Department will be treated the same way.

07Internal reporting is becoming the main route for outside verification

Of those three lines, the one whose shape is still to be settled is the bill protecting employees who report. The bill has co-sponsors. One of them said that innovation and accountability have to go hand in hand, and that employees should be able to raise concerns without risking their careers or being silenced by a non-disclosure agreement.

If it passes, one more route for outside verification exists. The timing of any vote is not set. Whether reports would reach anyone beyond the company has not been written down either. What is established is that co-sponsors have signed on.

What the courts have settled is also narrow. One ruling holds that a buyer may treat a vendor's own limits as a reliability problem. Nothing states that other buyers will do the same. Whether the company appeals is undecided. Narrow as it is, an organisation whose internal documents cite a vendor's limits as the basis for safety now has that sentence to re-read, and cannot itself decide when it stops holding.

Meanwhile the working days of organisations that have put AI into their processes carry on. What they can hold is the list of dependencies, the alternative they have already run once, and the record of why they chose. None of the three waits on a judgment.

Key Points ── 3 to take away
  1. The appeals court upheld the designation two to one and treated Claude's built-in usage restrictions themselves as a lack of reliability for military operations. A design that leaves safeguards with the vendor collapses at the buyer's decision.
  2. The dissent noted that 41 U.S.C. §4713 was drafted against hostile states and bad actors. The wider the authority reaches, the more a buyer needs its own record of why it chose a given supplier.
  3. In August a different federal court held a parallel designation unlawful. While the courts disagree, a buyer can lean only on an alternative it has already tested and on records it keeps itself.
Closing

An AI vendor's contractual limits do not override the buyer's procurement judgement. The mere fact that the limits were still in place became material for exclusion.

So the buyer's work does not end with reading the vendor's safeguards. It ends with holding, in-house, the list of dependencies, the alternative already tested, and the record of the selection. The tested alternative and the record can only be made before supply stops.

Sources & references
  1. The Epoch Times. Appeals Court Upholds Pentagon's Supply-Chain Risk Label on Anthropic. 25 September 2026.(Majority wording, the statutory basis in 41 U.S.C. §4713, the two-to-one composition and Judge Henderson's dissent)
  2. ABC News. Federal appeals court upholds Pentagon designation of Anthropic as supply chain risk. 25 September 2026.(Date and court, the majority's reliance on unreliability, and a separate federal court holding a parallel designation unlawful)
  3. The Next Web. US appeals court upholds Pentagon's supply chain risk label on Anthropic. 25 September 2026.(The demand for access for all lawful purposes, the substance of the restrictions the vendor retained, and the company weighing its options)
  4. Cornell Law School, Legal Information Institute (United States Code). 41 U.S. Code §4713 — Authorities relating to mitigating supply chain risks in the procurement of covered articles. Accessed 26 September 2026.(The authority to exclude on supply-chain risk grounds resting with the head of an executive agency)
  5. Deseret News. Bipartisan group of senators push to protect whistleblowers warning of AI capabilities. 25 September 2026.(Six or more co-sponsors for a bill protecting reporting by employees of AI companies, and a design under which non-disclosure agreements do not bar disclosure)
  6. European Commission, EudraLex Volume 4 GMP Annex 11: Computerised Systems. Annex 11, clause 3, Suppliers and Service Providers. 30 June 2011.(A supplier's capability and reliability as central to selection, audit necessity following from a risk assessment, and responsibilities stated in a formal agreement)